The Maharashtra Electricity Regulatory Commission has approved a review of the Scheduled Commencement of Supply Dates for solar projects by Avaada Energy. Delays in transmission infrastructure have pushed supply start dates back by 5 to 19 months. Developers may seek timeline extensions, but must address PPA requirements and financial implications.