The Central Electricity Regulatory Commission (CERC) has allowed a 50 MW solar project to retain its eligibility for a 100% waiver of interstate transmission system (ISTS) charges despite missing its commissioning deadline.
The Central Electricity Regulatory Commission (CERC) has allowed a 50 MW solar project to retain its eligibility for a 100% waiver of interstate transmission system (ISTS) charges despite missing its commissioning deadline.