The Gujarat Electricity Regulatory Commission (GERC) has rejected petitions from four ceramic tile manufacturers seeking extension of the scheduled commissioning dates (SCOD) for power evacuation infrastructure linked to their captive solar projects totaling 16 MW.The Commission observed that the developers had not provided sufficient documentary evidence showing they had undertaken construction activities related to the evacuation infrastructure.