The Appellate Tribunal for Electricity (APTEL) resolved a dispute involving three solar projects in Punjab, reducing their scheduled operation date extension from 90 to 79 days due to improper force majeure notice submissions. While upholding certain directions of the Punjab State Electricity Regulatory Commission, APTEL clarified the responsibilities of the developer, Mihit Solar.

The post APTEL Cuts SCOD Extension For 74 MW Punjab Solar Projects, Partly Modifies Regulatory Order appeared first on SolarQuarter.