On March 2, 2026, the Central Electricity Regulatory Commission addressed petitions from Serentica Renewables and ReNew Green Energy regarding the revocation of connectivity for renewable projects by CTUIL. The developers argued the cancellation was premature, citing delays from regulatory and environmental challenges. The Commission allowed them to proceed with commissioning while reviewing the case.